The grounds of challenge u/s 34(1) and (2) of Arbitration Ac, 1996 are distinct and independent from the grounds which are generally accepted by the Court for stay of an award under section 36(2) – Bharat Heavy Electricals Ltd. Vs. Optimal Power Synergy India Pvt. Ltd. – Calcutta High Court

Login with GoogleOR Username Password Remember Me     Forgot Password In case you've already logged in, click here […]

Scroll to Top