The grounds of challenge u/s 34(1) and (2) of Arbitration Ac, 1996 are distinct and independent from the grounds which are generally accepted by the Court for stay of an award under section 36(2) – Bharat Heavy Electricals Ltd. Vs. Optimal Power Synergy India Pvt. Ltd. – Calcutta High Court