NCLT rejects Resolution Plan of M2K Developers Pvt. Ltd. for the Corporate Debtor, M/s. Anil Mega Food Park Pvt. Ltd., for the reason that it cannot be effectively implemented – Ramchandra Dallaram Choudhary RP of Anil Mega Food Park Pvt. Ltd. – NCLT Ahmedabad Bench

Due to the National Highway in between the main road and unit of the Corporate Debtor, there exists no approach road. It is not possible for the RP, and the CoC to make available such an approach road leading to the unit of the Corporate Debtor which the Resolution Applicant is demanding through the Resolution Plan as approved by the CoC. The Adjudicating Authority held that in our considered opinion, such Resolution Plan, if at all approved, cannot be effectively implemented by anyone. The proviso to section 31(1) does not permit us to approve such conditional Resolution Plan. Hence, we reject the Resolution Plan submitted.

NCLT rejects Resolution Plan of M2K Developers Pvt. Ltd. for the Corporate Debtor, M/s. Anil Mega Food Park Pvt. Ltd., for the reason that it cannot be effectively implemented – Ramchandra Dallaram Choudhary RP of Anil Mega Food Park Pvt. Ltd. – NCLT Ahmedabad Bench Read Post »