Guidelines for Completion of Project – MP RERA

Madhya Pradesh Real Estate Regulatory Authority (RERA)

1. Obtain Completion Certificate from Competent Authority for the Project.

2. Mention actual project completion date as well as Completion Certificate issue date on the website.

3. Enclose scanned copy of Completion Certificate issued by the Competent Authority.

4. Submit Format 1C – Engineers Certificate on completion status.

5. Submit Format 2C – CA Certificate on completion status.

6. Enclose photographs (at least 5) in which completion of project along with external development can be ascertained.

7. These documents may be submitted within the period of submission of quarterly report for the quarter in which the project completed.


 


Act wise amended Rules and Regulations are available here: Click here for Rules & Regulation Dashboard.
For Notifications and Circulars, click here.
For bare acts, click here.

Go to Notifications and Circulars Dashboard