1[54D. (1) The pre-packaged insolvency resolution process shall be completed within a period of one hundred and twenty days from the pre-packaged insolvency commencement date.

(2) Without prejudice to sub-section (1), the resolution professional shall submit the resolution plan, as approved by the committee of creditors, to the Adjudicating Authority under sub-section (4) or sub-section (12), as the case may be, of section 54K, within a period of ninety days from the pre-packaged insolvency commencement date.

(3) Where no resolution plan is approved by the committee of creditors within the time period referred to in sub-section (2), the resolution professional shall, on the day after the expiry of such time period, file an application with the Adjudicating Authority for termination of the pre-packaged insolvency resolution process in such form and manner as may be specified.]


Reference

1. Ins. by the Insolvency and Bankruptcy Code (Amendment) Act, 2021, w.e.f. 04.04.2021.


Access complete Bare Act here and Notification and Circular here.

IBC Laws specifically does not make any warranties or representations as to the accuracy, completeness or adequacy of any such Material or the same being up-to-date. IBC Laws periodically updates the Material on this Site whenever amendments are made by Parliament. Refer disclaimer here.