Section 63 of Real Estate (Regulation and Development) Act, 2016 (RERA): Penalty for failure to comply with orders of Authority by promoter

The Real Estate (Regulation and Development) Act, 2016 Chapter-VIII Offences, Penalties and Adjudication Section 63: Penalty for […]

PDF & Print

The Real Estate (Regulation and Development) Act, 2016

Chapter-VIII Offences, Penalties and Adjudication

Section 63: Penalty for failure to comply with orders of Authority by promoter.

63. If any promoter, who fails to comply with, or contravenes any of the orders or directions of the Authority, he shall be liable to a penalty for every day during which such default continues, which may cumulatively extend up to five per cent., of the estimated cost of the real estate project as determined by the Authority.


Reference

*Effective from 01.05.2017.